The PMI-PBA (PMI Professional in Business Analysis) Certification Exam is a globally recognized certification exam that validates the knowledge and skills of professionals working in the field of business analysis. This certification is offered by the Project Management Institute (PMI), which is a leading organization in the field of project management. The PMI-PBA certification exam is designed to test the knowledge and skills required to effectively perform business analysis activities in a project environment.

 

NEW QUESTION # 27
A company is working on implementing a software application. They are converting their complex, in-house processes into the new system. The business analyst has been asked to analyze the processes.
Which technique should be followed?

  • A. Feasibility analysis
  • B. Interface analysis
  • C. MoSCoW
  • D. Requirements traceability

Answer: A

Explanation:
Explanation


NEW QUESTION # 28
During validation of a project solution, the business analyst discovers that a requirement has been altered.
Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.
Which corrective action should the business analyst take?

  • A. Discuss the change in the next stakeholder meeting.
  • B. Ask the developer to correct the logo as stated in the requirement.
  • C. Confront the stakeholder that requested the change.
  • D. Follow the change control process as defined in the business analysis plan.

Answer: D


NEW QUESTION # 29
A project team has completed the system use cases along with accompanying screen mockups. The business analyst schedules a review meeting with the client team to walk through the artifacts.
What is the purpose of this meeting?

  • A. To verify that the system is aligned with the quality requirements
  • B. To verify that the documents are aligned with the transition requirements
  • C. To validate that the documents are aligned with the solution requirements
  • D. To validate that the system is aligned with the stakeholder requirements

Answer: C


NEW QUESTION # 30
How should a business analyst determine whether a solution satisfies business requirements?

  • A. By reviewing the traceability matrix
  • B. By reviewing the results of user acceptance testing
  • C. By conducting a brainstorming session with end users
  • D. By evaluating the solution against the project charter

Answer: D


NEW QUESTION # 31
A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems.
Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?

  • A. Data modeling
  • B. Rules modeling
  • C. Enterprise modeling
  • D. Interface modeling

Answer: A

Explanation:
Explanation/Reference:


NEW QUESTION # 32
A firm implements SharePomt and the business analyst creates the requirements to develop a business analysis repository. In the requirements, the analyst describes a detailed workflow that includes appropriate stakeholders receiving email notifications of certain activities. The SharePoint team needs to know which activities should trigger the notification workflow.
Which workflow trigger should the business analyst incorporate?

  • A. Any change to the requirements matrix
  • B. Changes to test cases traced to requirements
  • C. Changes to stakeholder memberships
  • D. Change through project life cycle

Answer: A


NEW QUESTION # 33
The customer and Ihe business analyst are collaborating in the development of a solution scope. It is important for the customer to:

  • A. communicate changes to requirements only when they are completely defined.
  • B. challenge assessments of the cost and feasibility of requirements.
  • C. perform an alternatives analysis for requirements implementation
  • D. spend the time required to provide, clarify, and elaborate requirements.

Answer: D


NEW QUESTION # 34
After completing the requirements, the project manager and business analyst realize that the project scope is not feasible in the projected schedule The business analyst needs to review the amount of work the team is capable of delivering based on the approved project schedule.
Which prioritization technique should the business analyst use?

  • A. SWOT analysis
  • B. Weighted ranking
  • C. Time-boxing
  • D. Multivoting

Answer: D


NEW QUESTION # 35
A business analyst is working on a project to update the user interface for a legacy procurement system.
An end user raises concerns that the new solution will not support their core business processes.
How could the business analyst address the end user's concerns about the new interface?

  • A. Consult the stakeholder register to evaluate if the user has authority to influence the project.
  • B. Develop a prototype to gather functional requirements.
  • C. Document the business data objects using an entity relationship diagram.
  • D. Develop a use case package to support the user interface.

Answer: D


NEW QUESTION # 36
A business analyst has been assigned to a project team that is redesigning the company's website The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.
Which type of requirements are these?

  • A. Implemented
  • B. Tested
  • C. In-scope
  • D. Out-of-scope

Answer: D


NEW QUESTION # 37
When determining the value of a business case, which tool or technique should be used?

  • A. Variance analysis
  • B. SWOT analysis
  • C. Feasibility analysis
  • D. Cost-benefit analysis

Answer: D


NEW QUESTION # 38
The business analyst is conducting a feasibility study to understand how well a potential solution fits into the organization. What kind of feasibility assessment is the business analyst undertaking?

  • A. Operational
  • B. Technical
  • C. Time
  • D. Cost-effectiveness

Answer: A


NEW QUESTION # 39
A business analyst has captured all of the requirements from the various stakeholders within the organization and has compiled them into a complete list. After reviewing the list of requirements with the stakeholders, it is determined that the list of requirements is too large and will exceed the allotted budget.
Which tool or technique should the business analyst use with the stakeholders to prioritize the requirements to determine which requirements are approved, deferred, or rejected?

  • A. MoSCoW Analysis
  • B. SMART Goals
  • C. Timeboxing Analysis
  • D. SWOT Analysis

Answer: A


NEW QUESTION # 40
Which statement accurately depicts what changes can be made to requirements after they are baselined?

  • A. Requirements cannot be changed once user acceptance testing begins.
  • B. Requirements cannot be changed once development begins.
  • C. Requirements can be changed through a defined process.
  • D. Requirements can be changed only with sponsor approval.

Answer: C

Explanation:
The main output is the scope baseline, which consists of three documents; the scope statement (including both project and product requirements), the WBS(s), and the WBS dictionary. These are reviewed and upon approval, the scope baseline is created. Once that baseline has been approved, changes can only be made through a change control procedure. The scope baseline will be used to continually compare the actual results and work being done on the project to the original, approved scope.


NEW QUESTION # 41
The besl way lo ensure Ihe integrity of requirements is to:

  • A. establish a change control board, track the status of each requirement, and use a requirements management tool
  • B. use a requirements management tool, measure requirements volatility, and maintain a history of requirements changes
  • C. implement version control, maintain a history of requirements changes, and track the status of each requirement
  • D. establish a requirements baseline, establish a change control board, and label each requirement uniquely

Answer: C


NEW QUESTION # 42
A business analyst created requirements for production of a product extract file for several systems. After reviewing the complex systems and dividing the processes into manageable tasks, the business analyst is able to identify the tasks required to implement the deliverable.
Which analysis technique has the business analyst used?

  • A. Organization
  • B. Interface
  • C. Dependency
  • D. Decomposition

Answer: D


NEW QUESTION # 43
After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?

  • A. Change-driven approach
  • B. Analytical approach
  • C. Plan-driven approach
  • D. Waterfall approach

Answer: A

Explanation:
Explanation/Reference: https://www.slideshare.net/carlitos5071989/babok-v20


NEW QUESTION # 44
The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown structure (WBS) and schedule. However, a key requirement was not implemented in the release.
Which is a possible reason why the requirement was not implemented?

  • A. The schedule management plan was not updated with the change.
  • B. The requirements management plan was not updated with the change.
  • C. The scope management plan was not updated with the change.
  • D. The requirements traceability matrix was not updated with the change.

Answer: C


NEW QUESTION # 45
The requirements traceability matrix should primarily be used to:

  • A. address the responsibility owner for each requirement.
  • B. ensure that all requirements have been met.
  • C. define a convention to map the requirements to their sources.
  • D. identify the risks associated with dependent requirements

Answer: B


NEW QUESTION # 46
During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:

  • A. interviewed to understand how the user's work would be impacted.
  • B. identified as a stakeholder as part of the stakeholder analysis.
  • C. given the opportunity to review the user acceptance test scripts.
  • D. involved in the development and sign-off of the business requirements.

Answer: B


NEW QUESTION # 47
When a business analyst uses subject matter experts to define roles and identify influencers. which project artifact is created or updated?

  • A. RACI matrix
  • B. Stakeholder management plan
  • C. SWOT analysis
  • D. Stakeholder register

Answer: D


NEW QUESTION # 48
Once the requirements are compared to internal and external quality standards, what should the business analyst do next?

  • A. Set the priority of the requirements.
  • B. Communicate the requirements to stakeholders.
  • C. Ensure that the requirements are validated.
  • D. Baseline the requirements.

Answer: C

Explanation:
Explanation/Reference:


NEW QUESTION # 49
......

PMI-PBA Dumps With 100% Verified Q&As - Pass Guarantee or Full Refund: https://www.dumpsking.com/PMI-PBA-testking-dumps.html