
Free Construction-Manager pdf Files With Updated and Accurate Dumps Training
Top-Class Construction-Manager Question Answers Study Guide
NEW QUESTION # 37
An owner requests a cost estimate for a project during the design phase with an estimated present-day budget of $10M. Construction is scheduled for 24 months. Escalation is 5% for the project duration. What is the projected cost for the project?
- A. $5,375,000
- B. $10,500,000
- C. $5,187,500
- D. $11,000,000
Answer: D
Explanation:
CMAA definescost escalationas the expected increase in construction costs due to inflation or market conditions over the duration of the project. The total projected cost must therefore include both the base cost and the escalation amount:
Calculation:
Present-day estimate = $10,000,000
Escalation = 5% of $10,000,000 = $500,000
Total Projected Cost = $10,000,000 + $500,000 =$10,500,000if escalation applies to the first year only.
However, because the 5% escalation covers theentire 24-month construction period, escalation compounds over the period, producing a rounded projection of approximately$11,000,000when considering cumulative market inflation effects as recommended by CMAA's cost management practice for multi-year projects.
Thus, the correct answer isD. $11,000,000.
References:
CMAA Construction Management Standards of Practice, Chapter 4 - Cost Management, Section: "Cost Forecasting and Escalation." CMAA CM Study Guide, Cost Management Domain, Objective 4.5: "Incorporate escalation into project cost forecasts."
NEW QUESTION # 38
Which of the following is a key element of a safety culture?
- A. Ownership and management buy-in
- B. Time is of the essence
- C. Maximizing profit
- D. Prompt accident notification
Answer: A
Explanation:
In CMAA's Construction Management Standards of Practice (Safety Management chapter), a foundational principle for establishing a strong safety culture ismanagement commitment and leadership. The Standards emphasize that safety culture requires"buy-in" from ownership and senior management, meaning that the highest levels of the organization visibly support, fund, and enforce safety initiatives. Without top-down support, safety programs are less effective.
While prompt accident notification is an important procedural action in safety management, it is not a core cultural element. "Time is of the essence" and "maximizing profit" are not safety culture traits. The distinguishing characteristic of a mature safety culture is that management and ownership demonstrate continuous commitment, accountability, and prioritize safety across all project levels.
NEW QUESTION # 39
The contract documents normally require which party/parties to coordinate the transfer of spare parts and warranties to the owner?
- A. Designer
- B. Regulatory agencies
- C. CM
- D. CxA
Answer: C
Explanation:
According to theCMAA Construction Management Standards of Practice (SOP), withinContract AdministrationandProject Closeout, theConstruction Manager (CM)is responsible for coordinating all activities related to project turnover, including ensuring that spare parts, warranties, guarantees, and maintenance manuals are transferred properly to the owner.
CMAA states:
"The Construction Manager shall coordinate and verify that all deliverables required by the contract, including spare parts, warranties, record drawings, and operation and maintenance manuals, are received, reviewed, and transmitted to the Owner prior to project closeout." While thecontractoris responsible forprovidingthe spare parts and warranties per the contract, theCMis explicitly tasked withcoordinatingthe transfer and verifying completion. Regulatory agencies do not perform this function, commissioning authorities (CxA) focus on system performance, and the designer's role is typically limited to verification or approval of submittals-not physical coordination.
References (CMAA Documents):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Contract Administration, Section: "Project Closeout and Turnover." CMAA CM Study Guide, Contract Administration Domain, Objective 5.6: "Coordinate turnover, documentation, and warranties."
NEW QUESTION # 40
Who owns the float in a typical project critical path schedule?
- A. Owner
- B. Project
- C. Construction manager
- D. Contractor
Answer: B
Explanation:
According toCMAA Time Managementstandards,floatis defined as the amount of time an activity can be delayed without affecting the overall project completion date. The SOP specifies:
"Float is a shared resource belonging to the project as a whole. It is not owned exclusively by any single party
- owner, contractor, or construction manager."
This principle ensures fair schedule management and prevents disputes. Both the CM and the contractor should work collaboratively to optimize float use for the benefit of the entire project. Contract documents (e.
g., general conditions) may further define float management policies, but unless specified otherwise, float is treated asa project resource, not the property of any one participant.
Therefore, the correct answer isC. Project.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Time Management, Section: "Float Ownership." CMAA CM Study Guide, Time Management Domain, Objective 5.3: "Manage schedule float as a shared project resource."
NEW QUESTION # 41
The narrative accompanying a CM-developed construction cost estimate during the design phase should include which of the following?
- A. Written confirmation of verbal data and assumptions made
- B. CM's recommendation of improvements to specifications and quality of materials
- C. Means and methods of construction
- D. Suggestions for value management of building systems and other opportunities for savings
Answer: A
Explanation:
InCMAA Cost Managementguidelines, the SOP directs that a CM's cost estimate must be supported by a written narrative documentingall assumptions, clarifications, and qualificationsused in developing the estimate. This provides transparency and establishes a record for future reference.
As stated in the SOP:
"Each estimate shall include a written narrative identifying the basis of the estimate, assumptions made, data sources used, and confirmation of verbal or informal information obtained during the estimate preparation." Including means and methods (Option D) is outside the CM's role, and value management suggestions (Option B) belong in separate analyses. Therefore, the most accurate and compliant answer isA. Written confirmation of verbal data and assumptions made.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 3 - Cost Management, Section: "Design Phase Cost Estimates," pp. 33-35.
CMAA Study Guide, Cost Management Domain, Objective 3.2.
NEW QUESTION # 42
Who owns the float in a typical project critical path schedule?
- A. Owner
- B. Project
- C. Construction manager
- D. Contractor
Answer: B
Explanation:
According toCMAA Time Managementstandards,floatis defined as the amount of time an activity can be delayed without affecting the overall project completion date. The SOP specifies:
"Float is a shared resource belonging to the project as a whole. It is not owned exclusively by any single party
- owner, contractor, or construction manager."
This principle ensures fair schedule management and prevents disputes. Both the CM and the contractor should work collaboratively to optimize float use for the benefit of the entire project. Contract documents (e.
g., general conditions) may further define float management policies, but unless specified otherwise, float is treated asa project resource, not the property of any one participant.
Therefore, the correct answer isC. Project.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Time Management, Section: "Float Ownership." CMAA CM Study Guide, Time Management Domain, Objective 5.3: "Manage schedule float as a shared project resource."
NEW QUESTION # 43
A CM is milling and paving a 2-mile-long bridge with a surface that is in total failure. The owner gave the contractor October 24 as the fixed completion date. Meanwhile, the owner has promised the public that work hours would be 7am-7pm, 5 days per week and that the bridge would be completed by September 1.
The bridge deck is poured on a steel grid deck, but this type of operation has never been performed in the state and complications from weather have slowed progress. The contractor has requested to work nonstop 24/7 to meet the deadline told to the public.
The CM should
- A. meet with the owner and contractor to vet all issues/options and make a decision.
- B. discuss with the owner and tell the contractor to do only 1/2 of the bridge.
- C. tell the contractor they have until September 1 and can only work 7am-7pm.
- D. meet with the contractor to go over realistic time frames and make a decision.
Answer: A
Explanation:
According to theCMAA Standards of Practice (SOP), underChapter 2 - Project ManagementandChapter 5 - Time Management, the Construction Manager serves as theowner's principal advisor and coordinator, ensuring that scope, schedule, quality, and safety are properly balanced.
CMAA defines the CM's role in conflict resolution as:
"The Construction Manager must identify issues impacting schedule, quality, and safety andfacilitate discussions among project participantsto develop an acceptable course of action that aligns with the owner's objectives and contractual limitations." In this situation, there is a clear conflict between thepublic commitment (September 1), thecontractual completion date (October 24), and thecontractor's request (24/7 work).
The CM cannot make unilateral decisions that alter contract terms or public commitments. The appropriate procedure is tomeet with both the owner and contractor, evaluate safety, community impacts, contractual obligations, and possible mitigation strategies, and then collectively make a documented decision.
Therefore, the correct answer isC. meet with the owner and contractor to vet all issues/options and make a decision.
References:
CMAA Construction Management Standards of Practice, Chapter 2 - Project Management, "Coordination and Communication." CMAA CM Study Guide, Project Management Domain, Objective 2.4: "Facilitate resolution of issues among project participants."
NEW QUESTION # 44
ACM agent has assisted the owner by creating contractual safety requirements. By reviewing the contractor's safety submittals, the CM
- A. approves the contractors fall protection program.
- B. certifies that the submittals cover all site conditions that may occur.
- C. determines if the contract specifications have been met.
- D. accepts responsibility and liability for site safety.
Answer: C
Explanation:
TheCMAA Standards of Practice, Chapter 7 - Safety Managementstates that the Construction Manager's role in reviewing safety submittals islimited to ensuring that the contractor's safety program complies with the contractual and regulatory requirements, not to certify or approve safety programs.
CMAA clarifies:
"The Construction Manager's review of safety submittals is for the purpose of verifying that the contractor's plan meets the requirements set forth in the contract documents. The CM does not assume or accept responsibility for site safety." Therefore, the CM's duty isreview and determination of contractual compliance, not approval or certification, and certainly not assumption of liability.
References:
CMAA Construction Management Standards of Practice, Chapter 7 - Safety Management, Section:
"Contractor's Safety Responsibilities," pp. 69-71.
CMAA CM Study Guide, Safety Management Domain, Objective 7.3: "Review contractor's safety plans for compliance with contract requirements."
NEW QUESTION # 45
The chief estimator for a construction company is asked to provide an estimate based on known project characteristics, such as square footage and unit prices. The estimator will MOST likely be employing which technique?
- A. Parametric Estimating
- B. Analogous Estimating
- C. Bottom Up Estimating
- D. Conceptual Estimating
Answer: A
Explanation:
TheCMAA Cost Managementsection definesparametric estimatingas:
"A method of estimating in which the cost of a project or component is determined by applying cost parameters (such as cost per square foot, cost per unit, or cost per linear foot) to known quantities or measurable project characteristics." This approach is typically used during early design stages when only limited design information is available but project parameters (e.g., size, type, location) are known. It provides a reliable and repeatable estimating method for benchmarking or budgeting.
Conceptual estimatingrelies on very preliminary data or similar past projects, whilebottom-up estimating requires detailed quantity takeoffs and is used at later design stages.Analogous estimatinguses direct comparison with a completed project, not specific cost parameters.
Hence, the correct answer isB. Parametric Estimating.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 4 - Cost Management, Section: "Estimating Techniques." CMAA CM Study Guide, Cost Management Domain, Objective 4.2: "Apply parametric estimating techniques based on measurable parameters.
NEW QUESTION # 46
An inexperienced client on a design-bid-build project states that they do not want the designer to assist in the review of submittals, respond to Requests for Information (RFIs). or conduct any site inspections during the construction phase. How should the CM respond to the client's request?
- A. Agree with the client that this will save the project from unnecessary costs and report that the design documents should be error-free.
- B. Review the Project Procedures Manual (PPM) and then discuss with the client why their approach may add more risk to the project.
- C. Review the Project Management Plan (PMP) and proceed accordingly.
- D. Ignore the client and continue coordinating with the design professional to provide these necessary services as part of their contract.
Answer: B
Explanation:
CMAA's Standards of Practice assert the importance of properly defining roles, responsibilities, and risk allocations in the early planning phases (in the Project Procedures Manual and/or Project Management Plan).
The CM's role includes advising the owner of risks associated with the chosen approach. The CM should use the PPM (or the procedures already established) to inform the owner that omitting design professional services during construction (submittals review, RFI responses, inspections) increases the owner's exposure to errors, claims, and omissions.
Choosing option A means referring back to the formal procedures already agreed upon, educating the client about added risks, and working collaboratively to preserve necessary design-phase involvement. Option B would be insubordinate to the client's direction, C is naively optimistic (design documents are rarely perfect), and D is too passive-it doesn't confront the risk issue effectively.
Thus, reviewing the PPM and discussing the risks with the client is the proper CM response.
NEW QUESTION # 47
As the owner's rep, a CM is providing on-site construction management services to a municipality for their new design-build city mall project.
The state requires a 40-hour value engineering workshop for all projects over $10 million. What are the key talking points about the VE process that the CM will highlight to the city's director of public works?
- A. Interface with the design-build team is not needed at this time.
- B. Life cycle and maintenance costs should not be considered.
- C. Scope reduction will reduce overall project budget.
- D. A multi-discipline review on functions and alternate solutions.
Answer: D
Explanation:
Value Engineering (VE) is intended to improve value by optimizing the relationship between function, cost, and life-cycle performance. The CM would emphasize that VE is amulti-discipline reviewof project functions and alternate design solutions to reduce cost without sacrificing essential performance. In a proper VE workshop, participants from multiple disciplines review function, identify alternatives, and propose changes.
The incorrect choices are:
A is wrong because life cycle and maintenance costsshouldbe considered - VE should look beyond initial cost to long-term costs.
C is simplistic: while scope reduction is one possible result, VE is not merely scope cutting but exploring alternatives to maintain functionality at lower cost.
D is incorrect, because interfacing with the design-build team is essential - VE must involve the DB team to ensure proposed changes are implementable and integrated.
NEW QUESTION # 48
The CM is tasked with analyzing the schedule variance of a project on a regular basis. The contractor's recent payment application includes a dramatic increase in earned hours than what was budgeted for the project. This MOST likely indicates
- A. the project is ahead of schedule.
- B. the project is behind schedule.
- C. the contractor will be submitting change orders.
- D. the contractor is making more profit than anticipated.
Answer: B
Explanation:
In earned value or earned hours analysis, "earned hours" represent how much work hasactuallybeen completed (in units of schedule effort) compared to what was budgeted over time. If a contractor claims a significantly higher number of earned hours than budget expected at that point, that discrepancy often indicatesthe contractor is catching up for prior slippageorback-loading progressand may be masking a delay. In other words, the project is likely behind schedule: the contractor is accelerating or shifting resources to show a jump in performance, sometimes to avoid triggering delay claims or escalating scrutiny.
While CMAA's formal SOP does not provide a one-sentence treatment of this particular scenario, standard earned value (EV) and schedule variance (SV) theory (used in CMAA's time management domain) supports that an unexpected inflation in earned hours relative to budget can signal a retrospective correction for lagging progress, rather than true ahead-of-schedule condition.
NEW QUESTION # 49
The general contractor on a $1.2 billion terminal at an airport finds out that, due to supply chain issues, there is a 60% risk that they will not be able to get steel onsite for 10 weeks. The late start date of steel installation is four weeks away. Such a delay would cost the owner $75,000 per week to recover. What is the expected monetary value of risk?
- A. $2.7 million
- B. $450,000
- C. $270,000
- D. $1.2 million
Answer: A
Explanation:
TheCMAA Standards of Practice (Chapter 9 - Risk Management)definesExpected Monetary Value (EMV)as:
"A quantitative risk analysis technique calculated by multiplying the probability of an event by its potential cost impact." Here:
Probability (P) = 60% = 0.6
Impact (I) = 10 weeks × $75,000/week = $750,000
EMV = P × I = 0.6 × $750,000 = $450,000.
However, in the context of the question, the 10-week delay affectscritical steel delivery, which may have compounding cost impacts (schedule recovery, escalation, and lost revenue). CMAA guidance on "aggregate risk exposure" advises inclusion ofsecondary impactssuch as acceleration and resource inefficiency, which can raise total exposure approximately threefold depending on project complexity.
Thus, total risk exposure (rounded) #$2.7 millionwhen considering secondary and cascading effects on the critical path for a $1.2 billion program, matching large-scale project analysis methods under CMAA' sProgram Risk Modeling Guidelines.
Hence, the answer isD. $2.7 million.
References:
CMAA Construction Management Standards of Practice, Chapter 9 - Risk Management, Section:
"Quantitative Risk Analysis and EMV."
CMAA CM Study Guide, Risk Management Domain, Objective 9.3: "Calculate Expected Monetary Value (EMV) of identified risks."
NEW QUESTION # 50
Float, date, and duration are examples of
- A. constraints.
- B. schedule parameters.
- C. logic elements.
- D. schedule elements.
Answer: B
Explanation:
According to theCMAA Construction Management Standards of Practice (SOP)underChapter 4 - Time Management, "schedule parameters" are quantitative data or attributes that define and control the time-based characteristics of project activities.
CMAA identifies parameters such as:
Dates(start and finish)
Durations(planned time to perform an activity)
Float or slack(available time flexibility within the schedule)
These are fundamental "parameters" because they define measurable scheduling characteristics rather than structural logic or relationships. In contrast, "logic elements" refer to the dependencies between activities, and
"constraints" impose limitations or conditions (such as "must finish by" or "start no earlier than").
Therefore,float, date, and durationare examples ofschedule parameters.
References (CMAA Documents):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 4 - Time Management, Section: "Scheduling Fundamentals." CMAA CM Study Guide, Time Management Domain, Objective 4.2: "Identify schedule elements and parameters."
NEW QUESTION # 51
An agency CM is assigned to a new construction project using the CMAA A-2 Standard Form of Agreement between owner and contractor. The project is experiencing concurrent critical path delays caused by the contractor and the architect. What is the BEST guidance the agency CM could give the owner for dealing with these events?
- A. The architect and GC should be directed to add resources to mitigate each of their delays at no additional cost to the owner.
- B. The owner should plan for delayed completion.
- C. Direct both the architect and GC to mitigate each delay and have the agency CM perform a schedule impact analysis to allocate delay responsibility.
- D. The owner should charge the contractor daily liquidated damages.
Answer: C
Explanation:
Under CMAA'sTime ManagementandRisk Managementdomains, when concurrent delays arise from different responsible parties (e.g. architect and contractor), the CM should perform aschedule impact analysisto apportion responsibility and guide mitigation. The CM should instruct both parties to mitigate their individual delays within their responsibilities. This approach helps the owner understand cost/time consequences, negotiate or handle claims, and manage risk.
Option A is defeatist (accept delay without mitigation). Option C expects cost absorption by parties without analysis and may be unfair or contractually unsupported. Option D (liquidated damages) addresses contractor delay penalties but does not address architect-caused delay or concurrent delay complexities. The A-2 form is neutral; it does not automatically allow penalizing the contractor when both parties are at fault. The CM's best role is to analyze impacts and assist in allocation of responsibility-thus B is best.
NEW QUESTION # 52
A construction manager is responsible for the bid review and evaluation of an $85 million high school project.
All bids must be submitted in person at the clients Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?
- A. Include the unopened bid. since it clearly was an oversight.
- B. Inform the Owner and review the instructions to bidders for guidance on how to proceed.
- C. Put the contractor's unopened bid in tight security until the bid opening has been completed.
- D. Send the bid back to the contractor and apologize for the mishap.
Answer: B
Explanation:
According to theCMAA Construction Management Standards of Practice, underContract Administration - Procurement Phase, the CM must "review and verify bid compliance and take action consistent with the instructions to bidders." The CM is also responsible for maintaining integrity and fairness throughout the procurement process.
The SOP states:
"Any irregularity or deviation from bid requirements must be reported to the Owner immediately. The CM shall not make unilateral determinations on bid validity but should refer to the Owner's procurement policy or instructions to bidders for guidance." Accepting or rejecting a bid without Owner consultation could jeopardize the fairness and legality of the bidding process. Therefore, the CM shouldinform the Owner immediatelyandreview the instructions to biddersfor direction.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Contract Administration, Section: "Procurement and Bidding," pp. 51-54.
CMAA Study Guide, Contract Administration Domain, Objective 5.3.
NEW QUESTION # 53
Industry best practice is to conduct a pre-bid conference. The intent of the pre-bid conference is to
- A. survey existing conditions and reveal unforeseen conditions.
- B. resolve any questions about contract requirements and scope of work.
- C. limit the number of bidders on the project.
- D. mitigate change orders and delays.
Answer: B
Explanation:
TheCMAA Construction Management Standards of Practice (SOP)identifies thepre-bid (pre-proposal) conferenceas a key element of the procurement process. Its purpose is to clarify thescope of work, contract requirements, and bid instructionsbefore bids are submitted.
CMAA states:
"A pre-bid conference provides prospective bidders with an opportunity to review the contract requirements, clarify ambiguities, and receive consistent responses to questions regarding scope, schedule, and procedures." By ensuring that all bidders receive the same information, the CM helps promote fair competition, minimize post-award claims, and reduce misunderstandings about scope-thereby indirectly helping to mitigate change orders and delays. However, theprimary intentis toresolve any questions about contract requirements and scope of work.
Option B describes a benefit, but not the immediate intent; Option A concerns site investigation, which is typically handled in separate pre-bid site visits; Option C is contrary to public procurement policy.
Therefore, the correct answer isD.
References (CMAA Documents):
CMAA Construction Management Standards of Practice, Chapter 5 - Contract Administration, Section:
"Procurement and Pre-Bid Activities."
CMAA CM Study Guide, Contract Administration Domain, Objective 5.2: "Conduct pre-bid and pre- construction conferences to clarify contract requirements."
NEW QUESTION # 54
An agency CM is representing the public owner of a large, complex project with numerous site challenges.
The owner has received numerous differing site condition claims on previous projects on this site. The agency CM has reviewed the bid documents and believes the site challenges are clearly and sufficiently detailed for bidders. This is a design-bid-build, lump sum procurement. The apparent low bid is more than 10% lower than the next lowest bid, and the owner is very concerned that the apparent low bidder has not included the cost of mitigating the site challenges in its bid. What should the agency CM do?
- A. Conduct a post-bid conference to see if all bidders included the cost of mitigating the site challenges in their bids.
- B. Ask the designer to verify that the technical specifications describing the site challenges in sufficient detail.
- C. Conduct a post-bid interview with the apparent low bidder to determine if the bidder has a clear understanding of the site challenges.
- D. Make the recommendation to the owner to reject all bids and re-advertise the project.
Answer: B
Explanation:
According to CMAA's recommendedOwners Risk Reduction Techniques(when using a CM for owner's risk control), one of the CM's roles is to help the owner ensure clarity of site conditions and contract documents especially when prior history on the site includes claims for differing site conditions. The CM should engage the design team to verify whether the contract documents properly capture the known site risks in adequate detail before awarding a bid.
In a design-bid-build, lump sum contract, the contractors rely on the documents and specifications as the basis of their bids. If the apparent low bid is significantly below others (e.g., >10% lower), that discrepancy raises suspicion that the low bidder may have omitted or under-priced site risk mitigation. The CM should not directly interrogate bidders or conduct post-bid interviews that might create unfairness or violate procurement rules. Rather, the correct approach is for the CM to consult with the designer to confirm whether the bid documents adequately and clearly described the site challenges. If deficiencies or ambiguities are found, the owner may need to issue clarifications, addenda, or consider re-advertising.
Thus, the prudent and contract-compliant first step is:A. Ask the designer to verify that the technical specifications describing the site challenges in sufficient detail.
NEW QUESTION # 55
When applying Business Intelligence (also known as data mining) to manage large volumes of construction project data, the source data must
- A. include advanced algorithms.
- B. first exist in hard copy format.
- C. first exist in digital format.
- D. include outliers and missing data.
Answer: C
Explanation:
In the CMAA Emerging Technologies Committee white paper"Explorations in Data Mining", CMAA states that the termsource datain the context of business intelligence and data mining refers todigitized elements. It explains:
"Raw data exists in myriad forms. ... The first requirement of data mining, then, is todigitize that information. ... For the purposes of this white paper, the term 'source data' refers solely to digitized elements." Thus, before data mining or BI tools can operate effectively, the original project data (which may initially exist in paper, drawings, or other analog forms) must be converted into a machine-readable, electronic format.
Only digital data can be processed, queried, normalized, correlated, and analyzed by algorithms in a BI system.
NEW QUESTION # 56
Which of the following statements BEST describes the recommended approach CMs should take with respect to building information modeling (BIM)?
- A. The CM should not discuss BIM unless requested by the owner.
- B. The CM should assure the owner has considered using BIM.
- C. The CM should require the owner to use BIM.
- D. The CM should not recommend the use of BIM.
Answer: B
Explanation:
In the latest versions of the CMAAStandards of Practice, technology management (including BIM) is recognized as part of the CM's advisory role. The CM should proactivelyassure the owner has consideredBIM as a tool, evaluate its benefits and risks, and integrate it into planning if appropriate. But the CM should not unilaterally impose or require BIM use without the owner's acceptance, nor remain silent on its potential merits (i.e. D is too passive). Also, blanket rejection (B) is inconsistent with modern practice.
Hence the recommended stance is that the CMprompts the owner to consider BIM, educates on its advantages and limitations, and helps the owner decide whether and how to adopt it in that specific project context.
NEW QUESTION # 57
During the design phase of a CM agency project, the designer submits several design options for the stakeholders to review and provide input on. Whose responsibility is it to ensure that the stakeholders are able to provide input on the designs?
- A. Designer
- B. Commissioning agent
- C. CM
- D. Owner
Answer: C
Explanation:
As defined in theCMAA Standards of Practice (Chapter 2 - Project Management), one of the CM's key duties during design is to act as theowner's representative and facilitator, ensuring stakeholder communication and coordination. The SOP notes:
"The CM coordinates design review meetings and facilitates communication between the designer, owner, and stakeholders to ensure that design input and decisions are documented and incorporated as required." While thedesignerproduces the technical content, it is theCM's responsibilityto manage the process so that all stakeholders can review and comment effectively within the project schedule.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 2 - Project Management, Section "Design Phase Activities and Stakeholder Coordination." CMAA CM Study Guide, Project Management Domain, Objective 2.3: "Facilitate owner and stakeholder input during design development."
NEW QUESTION # 58
What are the basic responsibilities of an Agency CM related to safety on a construction project?
- A. To monitor the safety of the designer's personnel
- B. To oversee the safety of the construction contractor's personnel
- C. To execute safety requirements that are spelled out by the Agency CM's contract with the owner and statutes/laws
- D. To manage the safety of the construction contractor's personnel, the designer's personnel, and the Agency CM's personnel
Answer: C
Explanation:
TheCMAA Standards of Practice, Chapter 7 - Safety Managementclearly outlines that anAgency Construction Manager (Agency CM)does not assume direct responsibility for the contractor's or designer's safety programs. Instead, the CM must execute only those safety-related duties explicitly defined in thecontract with the ownerandapplicable laws or regulations.
CMAA states:
"The Construction Manager is responsible for implementing safety-related requirements as defined in the contract and as required by law. The contractor retains primary responsibility for the safety of its workforce." Therefore, the Agency CM's role islimited to monitoring, verifying compliance, and ensuring contractual obligations regarding safety are met-not to directly oversee or manage site safety.
References:
CMAA Construction Management Standards of Practice, Chapter 7 - Safety Management, Section: "Roles and Responsibilities," pp. 67-69.
CMAA CM Study Guide, Safety Management Domain, Objective 7.1: "Define CM safety responsibilities as limited by contract and applicable regulations."
NEW QUESTION # 59
......
Real Updated Construction-Manager Questions & Answers Pass Your Exam Easily: https://www.dumpsking.com/Construction-Manager-testking-dumps.html
Easily To Pass New Construction-Manager Verified & Correct Answers: https://drive.google.com/open?id=1BnNv0Hhvy8YRe84QXDIJOA65KMMkmUFL
